#1428 Crescent Tower B
Leveling matrix
Division 05 — Structural Steel
3 bids · 7 scope lines · normalized for exclusions
Leveled comparison
Scope line · source
Steelco Fabrication
Expired
rev B
FabriMid Industries
Basis
rev C
Iron & Co.
Current
rev B
Δ basis
05 12 00 — Structural steel frame
Spec 05 12 00 §1.3.A
$ 1,842,000
$ 1,786,500
$ 1,910,200
+6.9%
05 21 00 — Joists & deck
Spec 05 21 00 §1.3
$ 642,800
$ 618,200
$ 631,000
+4.0%
05 31 00 — Composite & roof deck
Spec 05 31 00 §2.2
$ 188,400
$ 174,200
$ 202,900
+7.7%
05 50 00 — Misc metals (rails, ladders)
A-501 §4
Excluded by Steelco
excluded
$ 74,200
$ 118,400
gap
05 51 00 — Galv stair stringers
RFI-014
Excluded by Steelco & Iron & Co. · carry as allowance
excluded
$ 74,200
excluded
conflict
05 75 00 — Decorative formed metal
Spec 05 75 00
Quantity mismatch — Iron & Co. carries 9 LF, FabriMid carries 30 LF
excluded
$ 2,800
$ 37,500
—
Subtotal
$ 2,861,600
$ 2,748,900
$ 2,920,100
—
Leveled total
$ 2,861,600
$ 2,548,900
$ 2,920,100
Apples-to-apples reconciliation.
Missing line items are filled with allowance from the sub that carries them. Steelco's bid expired 2026-04-12 — totals shown for reference only.